Renewable energy proposals map
To help provide an overview of renewable energy development in Perth and Kinross, we produce a series of maps based on our own database of renewable energy proposals.
The maps showing biomass, hydro, solar and wind energy proposals is updated every month. However, it will not contain all renewable energy proposals, nor will it reflect recent changes in status. Consequently, the map will never be 100% accurate. The maps are intended to provide an overview only. The maps show proposals which have been approved, awaiting consent, refused and withdrawn. We are working to resolve the problem. In the meantime if you use the links in the table below you will get information, including mapping, from our online database.
Once you have opened the map you should tick the box for the technology you are interested in. You can then use your mouse to hover over a proposal and this allows you to query information using the map screen by clicking on the point you want to query. When you click on the proposal you are interested in a window will open with information about that proposal. Should you want more information you can use the planning application reference number to search our online database. In addition more information about the larger proposals is shown below.
Wind energy
The table below shows the scale of the proposals operational, approved or in the planning system at 17 October 2014. You should be aware that as proposals develop, the size and status of proposals might change. The list only covers wind turbines greater than 25 metres in height or more than 100kw in installed capacity. You can also search the online database.
Application Number | Location | Development (Link to Online database) | Number of turbines | Height to blade tip (m) | Installed capacity (MW) | Status | ||
Total Installed capacity | 295+ | |||||||
Ref. No: 14/01686/SCRN | Site At Hilton Of Duncrievie Glenfarg | Proposed wind turbine | 1 | 34.2 | ||||
Ref. No: 14/01617/FLL | East Dron Wind Turbine Dron Bridge Of Earn | Erection of wind turbine and associated infrastructure | 1 | 74 | 0.8 | Pending consideration | ||
Ref. No: 14/01463/FLL | Land 450 Metres North West Of East Blair Farm Glenfarg | Erection of single wind turbine with associated works | Pending consideration | |||||
Ref. No: 14/01278/SCRN | Glentarkie Farm Glentarkie Strathmiglo Cupar KY14 7RU | Erection of a wind turbine | ||||||
Ref. No: 14/01236/FLL | 240 Metres South West Of Scottish Off Road Driving Centre Glentarkie Strathmiglo | Erection of wind turbine | Pending consideration | |||||
Ref. No: 14/01186/SCRN | Land 400 Metres North West Of Hill House Inchture | Erection of a wind turbine | ||||||
Ref. No: 14/01168/SCRN | Land 600 Metres North East Of Wester Bleaton Quarry Dalrunzion | Erection of 3 wind turbines | ||||||
Ref. No: 14/01120/FLL | Land 200 Metres North West Of Pairney Farm Auchterarder | Erection of wind turbine | Pending decision | |||||
Ref. No: 14/00837/FLL | Knowes Farm Dunning Perth PH2 0RB | Erection of 9 no, turbines and associated infrastructure | Pending consideration | |||||
Ref. No: 14/00627/FLL | Land 650 Metres North West Of Innernyte Farm Kinclaven | Erection of wind turbine and associated infrastructure | Pending decision | |||||
Ref. No: 14/00478/FLL | Drummick Farm Glenalmond Perth PH1 3SF | Installation of 2no wind turbines | Application approved | |||||
Ref. No: 14/00468/FLL | Colliston Farm Drunzie Glenfarg Perth PH2 9PE | Erection of a wind turbine and ancillary infrastructure | Pending decision | |||||
Ref. No: 14/00350/FLL | Land North West Of Easter Fordel Farm Glenfarg | Replacement of wind turbine (hub height 20m approx) with a wind turbine (hub height 35m approx) | Pending consideration | |||||
Ref. No: 14/00253/SCRN | Drummick Farm Glenalmond Perth PH1 3SF | Erection of 2 wind turbines | ||||||
Ref. No: 14/00097/FLM | Bandirran Wind Farm Balbeggie | Erection of 6 wind turbines, anemometer mast and ancillary works | Pending consideration | |||||
Ref. No: 13/02362/FLM | Creag A' Bhaird Wind Farm Amulree | Erection of 13 wind turbines and associated works and erection of two anemometer masts | Pending consideration | |||||
Ref. No: 13/02357/FLL | Land 800 Metres South East Of Montague Mill House Balbeggie | Erection of a wind turbine, siting of ancillary infrastructure and formation of access track and hardstanding area | Pending consideration | |||||
Ref. No: 13/02356/FLL | Outfield Farm Abernyte Perth PH14 9RA | Installation of a wind turbine (to replace turbine previously approved under Ref 11/00372/FLL) | Application approved | |||||
Ref. No: 13/02140/FLL | Land 150 Metres North West Of Netheraird Of Glasclunie Kinloch | Erection of wind turbine | Pending decision | |||||
Ref. No: 13/02021/SCRN | Land 250 Metres North West Of Craigieholm Burrelton | Erection of a single wind turbine | ||||||
Ref. No: 13/01902/SCRN | Drumfork Blacklunans | Erection of 500 kW wind turbine | ||||||
Ref. No: 13/01900/FLL | Hilton Of Aldie Aldie Kinross KY13 0QJ | Erection of two wind turbines | Application approved | |||||
Ref. No: 13/01896/FLL | Land 390 Metres South East Of The Bothy Newburgh | Erection of a wind turbine | Pending decision | |||||
Ref. No: 13/01803/FLL | Craiglaw Farm Rumbling Bridge Kinross KY13 0QQ | Erection of two wind turbines associated plant and access track. | Application approved | |||||
Ref. No: 13/01467/SCRN | Mill Of Montague Balbeggie Balbeggie Perth PH2 7PR | Erection of a wind turbine | ||||||
Ref. No: 13/01449/SCRN | Strelitz Pendagle Burrelton Blairgowrie PH13 9PY | Erection of a wind turbine | ||||||
Ref. No: 13/01367/SCRN | Land 460 Metres South West Of Rossie Ochil Home Farm Forgandenny | Screening opinion for 400kw wind turbine and associated ancillary structures on land | ||||||
Ref. No: 13/01325/SCRN | Shire-End Farm Path Of Condie Perth PH2 9DR | Proposed single medium-scaled wind turbine | ||||||
Ref. No: 13/01288/FLL | Land 400 Metres South West Of Drumside Dunning | Erection of a single wind turbine with temporary access track and substation | Application approved | |||||
Ref. No: 13/01230/FLL | Land 700 Metres South Of Glenbran Farm Abernyte | Erection of wind turbine and ancillary works | Application approved | |||||
Ref. No: 13/01125/SCRN | Balado Bridge Poultry Farm Balado | Erection of wind turbine | ||||||
Ref. No: 13/00921/SCRN | Land 570 Metres North West Of Craigmiglo Cottage Milnathort | Erection of wind turbine | ||||||
Ref. No: 13/00922/SCRN | Old Fargie Farm Glenfarg Perth PH2 9QF | Erection of wind turbine | ||||||
Ref. No: 13/00889/SCRN | Meikle Fieldie Glenfarg Perth PH2 9PZ | Erection of a wind turbine | ||||||
Ref. No: 13/00798/FLL | Land 350 Metres South West Of Wester Essendy Farm Wester Essendy | Erection of two wind turbines | 2 | 32 | 0.06 | Application approved | ||
Ref. No: 13/00766/SCRN | Carden Farm Aldie Kinross KY13 0QH | Screening Opinion - Erection of two wind turbines | ||||||
Ref. No: 13/00767/SCRN | South Kilduff Wind Farm Fossoway | Screening Opinion - Erection of two wind turbines | ||||||
Ref. No: 13/00768/SCRN | Craiglaw Farm Rumbling Bridge Kinross KY13 0QQ | Screening Opinion - Erection of two wind turbines | ||||||
Ref. No: 13/00715/SCRN | Netheraird Of Glasclune Kinloch Blairgowrie PH10 6SF | Erection of wind turbine | ||||||
Ref. No: 13/00693/FLL | Land 1200 Metres South East Of The House On The Hill Kettins | Installation of a wind turbine and associated infrastructure | Application approved | |||||
Ref. No: 13/00575/SCRN | Gourdie Farm Spittalfield Perth PH1 4LF | Erection of wind turbine | 1 | 80 | 0.8 | Screening | ||
Ref. No: 13/00576/SCRN | Coupar Grange House Bendochy Blairgowrie PH13 9HT | Erection of single wind turbine | Screening | |||||
Ref. No: 13/00414/FLL | Land 500 Metres North West Of East Blair Farm Glenfarg | Erection of a single wind turbine | 2 | 64 | 0.5 | Application approved | ||
Ref. No: 13/00391/SCRN | Netherton Farm Blackford Auchterarder PH4 1QU | Erection of 2 wind turbines | Screening | |||||
Ref. No: 13/00297/SCRN | Land At Kinvaird (1km NW Of Moneydie And 3.4km West Of Luncarty) | Erection of a wind turbine | Screening | |||||
Ref. No: 13/00272/SCRN | Land 1200 Metres South East Of The House On The Hill Kettins | Erection of second wind turbine | 1 | 46 | 0.25 | Screening | ||
Ref. No: 13/00220/FLL | Land At Easter Logie Forneth | Erection of a wind turbine and associated infrastructure | 1 | 49 | 0.1 | Pending consideration | ||
Ref. No: 13/00162/SCRN | Land 400 Metres South West Of Drumside Dunning | Erection of a wind turbine | 1 | 49.5 | 0.225 | Screening | ||
Ref. No: 13/00063/SCRN | Land North West Of Easter Fordel Farm Glenfarg | Installation of wind turbine | 1 | 99 | 0.8 | Screening | ||
Ref. No: 12/02200/FLL | Land 600 Metres North East Of Thorntonhill Fossoway | Erection of a wind turbine | 1 | 45.5 | 0.225 | Application approved | ||
Ref. No: 12/01336/FLL | Loyal Farm Alyth Blairgowrie PH11 8JQ | Erection of a wind turbine and associated access track and meter house | 1 | 47 | 0.225 | Application approved | ||
Ref. No: 12/01934/FLL | The Corb Bridge Of Cally Blairgowrie PH10 7JX | Erection of a wind turbine, meter house and associated access track | 1 | 84 | 0.85 | Application approved | ||
Ref. No: 12/01544/FLL | Williamfield Greenloaning Dunblane FK15 0NA | Erection of a wind turbine | 1 | 45 | 0.4 | Application approved | ||
Ref. No: 12/01504/FLL | East Gormack Farm Blairgowrie | Modification of existing consent 10/01825/FLL to erect a wind turbine (change of model and increase in height) | Application approved | |||||
Ref. No: 12/01368/FLL | Land To The North Of Tormaukin Grazings Glendevon | Erection of a wind turbine | Application approved | |||||
Ref. No: 12/01301/FLL | Vane Farm Nature Centre Kinross KY13 9LX | Erection of a wind turbine | Application approved | |||||
Ref. No: 12/01283/FLL | Land 300 Metres North West Of Chapelhill Trinity Gask | Erection of a dwellinghouse and wind turbine | Application approved | |||||
Ref. No: 12/01082/FLL | Dunduff House Braco Dunblane FK15 9LA | Erection of two wind turbines (modification of 11/01692/FLL) | Application approved | |||||
Ref. No: 12/01021/FLL | Land North West Of Easter Fordel Farm Glenfarg | Erection of a wind turbine | Application approved | |||||
Ref. No: 12/00857/FLL | Land 1200 Metres South East Of The House On The Hill Kettins | Erection of a wind turbine | 1 | 45.5 | 0.4 | Application approved | ||
Ref. No: 12/00735/FLL | Muirton Of Drumlochy Blairgowrie PH10 6TD | Erection of a wind turbine | Application approved | |||||
Ref. No: 12/00658/FLL | Land 800 Metres South West Of Glenlomond Farm Glenlomond | Erection of 3 wind turbines | Application approved | |||||
Ref. No: 12/00321/FLL | Land 140 Metres North East Of Ferns Cloquhat Bridge Of Cally | Erection of a wind turbine | 3 | 84 | 2.4 | Application approved | ||
Ref. No: 12/00245/FLL | Land 2700 Metres North West Of Camsericht Lodge Rannoch | Erection of wind turbine | Application approved | |||||
Ref. No: 12/00233/FLL | Barnhill Farm Powmill | Erection of a single wind turbine | 2 | 41.5 | 0.2 | |||
Ref. No: 11/02152/FLL | Land 300 Metres North West Of Wester Kinloch Farm Cottage Kinloch | Erection of a wind turbine | Application approved | |||||
Ref. No: 11/02053/FLL | Bankhead Farm Fossoway Kinross KY13 0PW | Erection of two wind turbines | 2 | 23 | 0.2 | Application approved | ||
Ref. No: 11/01980/FLL | Land 370 Metres West Of Hill Of Lethendy Farm Cottage Meikleour | Erection of a wind turbine and associated works | Application approved | |||||
Ref. No: 11/01930/FLL | Site South Of The Upper And Lower Glendevon Reservoirs Glendevon | Windfarm extension comprising two additional turbines and ancillary works | 2 | 102 | 4 | Application approved | ||
Ref. No: 11/01739/FLL | Cuthill Towers Farm Cuthill Towers Glenfarg Kinross KY13 9SH | Installation of a single wind turbine | Application approved | |||||
Ref. No: 11/01692/FLL | Dunduff House Braco Dunblane FK15 9LA | Erection of two wind turbines | 2 | 46.5 | 0.2 | Application approved | ||
Ref. No: 11/01542/FLL | 7 Netherhall Steadings Milnathort Kinross KY13 0RL | Erection of a wind turbine to serve Plot 8 | Application approved | |||||
Ref. No: 11/01500/FLL | Nether Obney Farm Bankfoot Perth PH1 4AT | Modification of existing consent (10/00515/FLL) Erection of two wind turbines | Application approved | |||||
Ref. No: 11/01470/FLL | Gellybank Farmhouse Kinross KY13 0LE | Erection of a wind turbine and formation of road entrance and driveway (Modification of consent 10/00124/FUL) | Application approved | |||||
Ref. No: 11/01464/FLL | Mid Cambushinnie Farm Cromlix Dunblane FK15 9JU | Erection of 2 wind turbines | Application approved | |||||
Ref. No: 11/01318/FLL | Shandry Farm Rait Perth PH2 7SF | Erection of two wind turbines and associated access track | Application approved | |||||
Ref. No: 11/01302/FLL | Land At Hilton Hill Bamff Estate Alyth | Installation of a wind turbine | Application approved | |||||
Ref. No: 11/01060/FLM | Calliachar Wind Farm Amulree | Variation of previous consent (07/02617/FUL) to increase 14 wind turbine tower heights from 59m to up to 63.3m, rotor diameter from 82m to up to 93m and overall blade tip height from 100m to up to 109.8m | 14 | 109.8 | 32.2 | Operational | ||
Ref. No: 11/00798/FLL | Woodhead Farm Blairgowrie PH10 6TB | Installation of a wind turbine | Application approved | |||||
Ref. No: 11/00766/FLL | Land 2500 Metres South East Of Balmacnaughton Remony | Erection of 2 wind turbines at Urlar Estate | 2 | 46.9 | 0.45 | Application approved | ||
Ref. No: 11/00736/FLL | Mawcarse Farm Mawcarse Kinross KY13 9SJ | Modification of existing consent (10/00235/FLL) to change turbine type and specification | Application approved | |||||
Ref. No: 11/00480/FLL | The Steading Wester Essendy PH10 6RA | Modification of existing consent 10/00276/FLL (Erection of 3 wind turbines) | Application approved | |||||
Ref. No: 11/00002/PSN | Land 1200 Metres South East Of The House On The Hill Kettins | Erection of a single wind turbine up to 80m tip height | Application approved | |||||
Ref. No: 11/00394/FLL | Muir O Lea Farm Crieff PH7 3RJ | Erection of 2 wind turbines and associated meter housing | Application approved | |||||
Ref. No: 11/00372/FLL | Outfield Farm Abernyte Perth PH14 9RA | Installation of a wind turbine | Application approved | |||||
Ref. No: 11/00251/FLL | Plains Farm Path Of Condie Perth PH2 9QW | Erection of a wind turbine | Application approved | |||||
Ref. No: 11/00024/FLL | Easter Tullyneddie Farm Forneth PH10 6SL | Installation of a 10kW Evoco wind turbine | Application approved | |||||
Ref. No: 11/00009/FLL | Easter Fossoway Carnbo Kinross KY13 0PA | Erection of a wind turbine | Application approved | |||||
Ref. No: 10/02151/FLL | Muirton Of Drumlochy Blairgowrie PH10 6TD | Erection of 10kW wind turbine | Application approved | |||||
Ref. No: 10/01919/FLL | Thorntonhill Fossoway KY13 0PB | Erection of 10kW evoco wind turbine | Application approved | |||||
Ref. No: 10/01904/FLL | Pairney Farm Auchterarder PH3 1DT | Erection of a wind turbine | Application approved | |||||
Ref. No: 10/01855/FLL | Baldinnies Farm Dunning Perth PH2 0QQ | Installation of 2 x 15kw wind turbines to generate electricity | Application approved | |||||
Ref. No: 10/01825/FLL | East Gormack Farm Blairgowrie | Erection of a wind turbine and associated development | 1 | 33.4 | 0.33 | Application approved | ||
Ref. No: 10/01672/FLL | Stewart Tower Farm Airntully Stanley Perth PH1 4PJ | Erection of a wind turbine | 1 | 66.6 | 0.33 | Application approved | ||
Ref. No: 10/01601/FLL | Arnbog Farm Meigle Blairgowrie PH12 8QT | Erection of 3 wind turbines (19.33 metres in overall height) | Application approved | |||||
Ref. No: 10/01545/FLL | Greenhead Farmhouse The Arnot Estate Leslie Glenrothes KY6 3JQ | Erection of a 35 metre high wind turbine | Application approved | |||||
Ref. No: 10/01433/FLL | Stanley Farm Stanley Perth PH1 4PG | Installation of a 15kw wind turbine | Application approved | |||||
Ref. No: 10/01425/FLL | Sauchie Farm St Davids Madderty Crieff PH7 3PP | Installation of a 15kw wind turbine | Application approved | |||||
Ref. No: 10/01333/FLL | Coldrach Blacklunans Blairgowrie PH10 7LA | Erection of a 15m high wind turbine | Application approved | |||||
Ref. No: 10/01304/FLL | Gracefield St Martins Perth PH2 6AW | Erection of 11kw wind turbine | Application approved | |||||
Ref. No: 10/01271/FLL | Touchie Farm Milnathort KY13 0RS | Erection of two wind turbines (modification of 08/00986/FUL; change of turbine type) | Application approved | |||||
Ref. No: 10/01001/FLL | Flowerdale Farm Kinrossie Perth PH2 6HX | Installation of a wind turbine | Application approved | |||||
Ref. No: 10/00962/FLL | The Stables Donafuil Farm Coshieville Aberfeldy PH15 2LE | Erection of a wind turbine | Application approved | |||||
Ref. No: 10/00954/FLL | Conland Farm Glenfarg Perth PH2 9QG | Erection of a wind turbine | Application approved | |||||
Ref. No: 10/00876/FLL | Welton Of Creuchies Farmhouse Alyth Blairgowrie PH11 8LB | Erection of four wind turbines, access road and associated infrastructure | 4 | 99.5 | 9.2 | Application approved | ||
Ref. No: 10/00861/FLL | Gallowmyre House Pitroddie Perth PH2 7NU | Erection of a 6kw wind turbine | Application approved | |||||
Ref. No: 10/00789/FLL | Land At The Stables Longforgan | Modification of existing consent 09/02007/FLL - Erection of a wind turbine | Application approved | |||||
Ref. No: 10/00611/FLL | Turflundie Abernethy Perth PH2 9LS | Erection of a two 11kw wind turbines | Application approved | |||||
| Nether Obney Farm Bankfoot Perth PH1 4AT |
| Application approved | |||||
Ref. No: 10/00502/FLL | Craighead Path Of Condie Perth PH2 9DR | Erection of 15kW wind turbine (hub height 15 metres) | Application approved | |||||
Ref. No: 10/00448/FLL | East Busby Farm Methven PH1 3SY | Erection of a wind turbine | ||||||
Ref. No: 10/00397/FLL | Mid Cambushinnie Farm Cromlix Dunblane FK15 9JU | Erection of 2 wind turbines | Application approved | |||||
Ref. No: 10/00276/FLL | The Steading Wester Essendy PH10 6RA | Erect 3 x 15kw wind turbines | Application approved | |||||
Ref. No: 10/00235/FLL | Mawcarse Farm Mawcarse Kinross KY13 9SJ | Erection of a 15kw wind turbine | Application approved | |||||
Ref. No: 10/00178/FLL | West Haugh Kinclaven Perth PH1 4QR | Replacement of wind turbine | Application approved | |||||
Ref. No: 10/00124/FLL | Gellybank Farm Kinross KY13 0LE | Erection of a wind turbine and formation of road entrance and driveway | Application approved | |||||
Ref. No: 10/00102/FLL | Islabank Farm Meikleour Blairgowrie PH13 9HL | Erection of a wind turbine | Application approved | |||||
Ref. No: 09/02198/FLL | Barnhill Farm Powmill Dollar FK14 7NS | Erection of 3 x 15kw wind turbines | Application approved | |||||
Ref. No: 09/02158/FLL | Drumcairnie Main Road Aberuthven Auchterarder PH3 1HE | Erection of a 15kw wind turbine | Application approved | |||||
Ref. No: 09/02078/FLL | Carsefoot Drum Kinross KY13 0PP | Erection of a 15kw wind turbine | Application approved | |||||
Ref. No: 09/02060/FLL | Ledlation Farm Milnathort KY13 0RS | Erection of 4 x 15kw wind turbines | Application approved | |||||
Ref. No: 09/02052/FLL | Braco Castle Danduff House Braco Dunblane FK15 9LA | Erection of four wind turbines | Application approved | |||||
Ref. No: 09/02007/FLL | Land At The Stables Longforgan | Erection of a single 15kw wind turbine. | Application approved | |||||
Ref. No: 09/01795/FLL | Abbey Farm Madderty Crieff PH7 3PA | Erection of a 15m high wind turbine | Application approved | |||||
Ref. No: 09/01655/FLL | Land 620 Metres North West Of Crofthead Braco | Erection of 2 wind turbines | Application approved | |||||
Ref. No: 09/01534/FLL | Nivingston House Cleish | Erection of a wind turbine | Application approved | |||||
Ref. No: 09/01418/FLL | Aim Development Inchcape House Inchcape Place Perth PH1 3DU | Erection of vertical axis wind turbine | Application approved | |||||
Ref. No: 09/01297/FLL | Site At Oakbank Mill Lade Keithbank Weir Blairgowrie | Installation of small hydro electric turbine generator within the existing Lade | Application approved | |||||
Ref. No: 09/01295/FLL | The Old Crossing House Balgowan Tibbermore Perth PH1 1QW | Demolition, alterations and extensions to house, erect new stone boundary walls and wind turbine | Application approved | |||||
Ref. No: 09/01213/FLL | East Busby Farm Methven PH1 3SY | Erection of a wind turbine | Application approved | |||||
Ref. No: 09/01149/FLL | Balneathal Farmhouse Easter Balgedie Kinross KY13 9HQ | Erection of a 15kw wind turbine | Application approved | |||||
Ref. No: 09/01130/FLL | East Fordel Farm Glenfarg Perth PH2 9QQ | Erection of a wind turbine | Application approved | |||||
Ref. No: 09/01057/FLL | Scottish Hydro Electric Plc Ruthvenfield Way Inveralmond Industrial Estate Perth PH1 3UF | Installation of solar panels and erection of a wind turbine | Application approved | |||||
Ref. No: 09/01006/FLL | Hilton Of Duncrievie Duncrievie Glenfarg Perth PH2 9PD | Erection of a wind turbine | Application approved | |||||
Ref. No: 09/00861/FUL | Zwetsloot Old Schoolhouse Thorngreen Road Kinrossie Perth PH2 6HP | Removal of existing and erection of a new wind turbine on land at | Application approved | |||||
Ref. No: 09/00828/MOD | Carsefoot Drum Kinross KY13 0PP | Modification of existing consent (09/00175/FUL) relocation of a 15m monopole wind turbine | Application approved | |||||
Ref. No: 09/00835/FLL | Newlands Farm House Milnathort Kinross | Erection of 3 wind turbines | Application approved | |||||
Ref. No: 09/00833/FLL | Newlands Farm House Milnathort Kinross KY13 9SL | Erection of a wind turbine | Application approved | |||||
Ref. No: 09/00803/FUL | East Busby Farm Methven PH1 3SY | Erection of wind turbine | Application approved | |||||
Ref. No: 09/00701/FUL | Glenvale Kinross KY13 9HG | Erection of a single 15kw wind turbine | Application approved | |||||
Ref. No: 09/00660/FLL | Netherhall Farm Kinross KY13 0RL | Erection of wind turbine | Application approved | |||||
Ref. No: 09/00175/FUL | Carsefoot Drum Kinross KY13 0PP | Erection of a monopole wind turbine | Application approved | |||||
Ref. No: 09/00154/FUL | Tesco Stores Ltd Crieff Road Perth PH1 2NR | Erection of 2 temporary micro wind turbines (for a period of 15 years) | Application approved | |||||
Ref. No: 08/02311/FUL | Hoodshill Fossoway Kinross KY13 0PW | Erection of wind turbine | Application approved | |||||
Ref. No: 08/02191/FUL | Buchal Farm Alyth Blairgowrie PH11 8JS | Erection of a wind turbine | Application approved | |||||
Ref. No: 08/02158/FUL | Blairstruie House Glenfarg Perth PH2 9QQ | Erection of a wind turbine | Application approved | |||||
Ref. No: 08/01907/FUL | Easter Gatherleys Dunning Perth PH2 0RD | Erection of small scale wind turbine with associated works | Application approved | |||||
Ref. No: 08/01800/FU | Kennels Cottage Abernyte Perth PH14 9SX | Erection of a wind turbine | Application approved | |||||
Ref. No: 08/01768/FUL | Coulshill Farm Auchterarder PH3 1PP | Installation of 48kw wind turbine | Application approved | |||||
Ref. No: 08/01753/FUL | West Brackley Farm Kinross KY13 9LU | Erection of a wind turbine | Application approved | |||||
Ref. No: 08/01651/FUL | Turret Water Treatment Works Crieff | Erection of a turbine and chemical dosing building | Application approved | |||||
Ref. No: 08/01627/FUL | Quilts Farm Dunning Perth PH2 0RB | Alterations and extension to dwellinghouse/stable and erection of domestic wind turbine | Application approved | |||||
Ref. No: 08/01424/MOD | Woodend Cottage Forgandenny Perth PH2 9ES | Modification of existing consent (01/00805/MOD) change of house type and erection of garage/workshop and 15m wind turbine | Application approved | |||||
Ref. No: 08/01422/FUL | Pitmeadow Farm Dunning Perth PH2 0RA | Erection of wind turbine on 15 metre mast | Application approved | |||||
Ref. No: 08/01334/FUL | Former Steading Head Dyke Auchterarder | Erection of wind turbine | Application approved | |||||
Ref. No: 08/00986/FUL | Touchie Farm Kinross KY13 0RS | Erection of 2 micro wind turbines | Application approved | |||||
Ref. No: 08/00533/FUL | Stronachie House Forgandenny Perth PH2 9DW | Installation of a 12m wind turbine | Application approved | |||||
Ref. No: 07/02468/FUL | Fairfield Duncrievie Glenfarg Perth PH2 9PD | Erection of a wind turbine and solar panels | Application approved | |||||
Ref. No: 07/01981/FUL | Auchtergaven Manse Tulliebelton Road Bankfoot Perth PH1 4BS | Erection two wind turbines | Application approved | |||||
Ref. No: 07/01751/FUL | Tesco Stores Ltd Edinburgh Road Perth PH2 8DX | Erection of a 10.6m high micro wind turbine (6kw) for 15 years | Application approved | |||||
Ref. No: 07/01537/FUL | Downham Farm Coupar Angus Blairgowrie PH13 9EY | Proposed conversion of farm workshop and store into dwellinghouse with associated garden, garages and wind turbine | Application approved | |||||
Ref. No: 07/00695/FUL | Kaimes Cottage Braco Dunblane FK15 9LG | Erection of a 12m wind turbine | Application approved | |||||
Ref. No: 07/00273/FUL | Blackcraig Farm Cottage Perth PH2 7PJ | Erection of a wind turbine | Application approved | |||||
Ref. No: 07/00023/FUL | Ormiston Wester Essendy Blairgowrie PH10 6RD | Installation of a micro wind turbine and formation of a vehicular access | Application approved | |||||
Ref. No: 06/02710/FUL | Whitehills Farm Blackford PH4 1RQ | Fitting of wind turbine on apex of garage roof | Application approved | |||||
Ref. No: 06/02662/FUL | Auchloy Farm Crieff PH7 3NG | Demolition of existing farmhouse and part of steading and erection of a replacement dwellinghouse and wind turbine | Application approved | |||||
Ref. No: 06/02630/FUL | Ballintuim Strathtummel PH16 5RS | Erection of a free standing domestic wind turbine | Application approved | |||||
Ref. No: 06/02506/FUL | Summerfield Glenfarg Perth PH2 9QD | Erection of a domestic wind turbine | Application approved | |||||
Ref. No: 06/02283/FUL | Brackenbrae Aberargie Perth PH2 9NE | Erection of a wind turbine | Application approved | |||||
Ref. No: 06/01940/FUL | Tullybelton House Bankfoot Perth PH1 4DH | Erection of new 25m high 50kw wind turbine | Application approved | |||||
Ref. No: 06/01837/FUL | Turflundie Abernethy Perth PH2 9LS | Erection of wind turbine on a 9m self-supporting mast (Proven Energy 6kw) | Application approved | |||||
Ref. No: 06/01399/FUL | Site A Dunsinnan Road Wolfhill Perth | Installation of a wind turbine | Application approved | |||||
Ref. No: 05/02407/FUL | Village Hall Hall Road Guildtown Perth | Erection of a micro wind turbine | Application approved | |||||
Ref. No: 05/02328/FUL | Shenavail Camserney Aberfeldy Perthshire PH15 2JF | Erection of a domestic wind turbine | Application approved | |||||
Ref. No: 05/02304/FUL | West Third Radio Mast Site Braco Dunblane Perthshire | Installation of shift wind turbine | Application approved | |||||
Ref. No: 05/01407/FUL | Land At Douranside Milnathort Kinross KY13 0RP | Erection of a wind turbine to provide electricity to dwellinghouse | Application approved | |||||
Ref. No: 05/01142/FUL | Kercock Farm Stanley Perth PH1 4QR | Erection of wind turbine at proposed new dwellinghouse (05/00269/FUL) | Application approved | |||||
Ref. No: 05/01061/FUL | Land At Green Knowes By Glendevon | Erection of 18 wind turbines and associated infrastructure, including borrow pits, control building, met mast, access tracks, access to A823 and temporary laydown areas | 18 | 93 | 36 | Operational | ||
Ref. No: 05/00752/FUL | Lochelbank | 12 | 91 | 16 | Operational | |||
Ref. No: 05/00689/FUL | Dunskiag Aberfeldy Perthshire PH15 2EX | Installation of a wind turbine on a 15m tower | Application approved | |||||
Ref. No: 05/00404/FUL | 200 Dunkeld Road Perth PH1 3GH | Erection of a wind turbine | Application approved | |||||
Ref. No: 05/00396/FUL | The Cottage At Inveralmond House 200 Dunkeld Road Perth PH1 3AQ | Erection of a wind turbine | Application approved | |||||
Ref. No: 05/00395/FUL | Central Stores Scottish Hydro Electric Plc Ruthvenfield Way Inveralmond Industrial Estate Perth PH1 3UF | Erection of a wind turbine | Application approved | |||||
Ref. No: 05/00394/FUL | Inveralmond House Scottish Hydro Electric Plc Dunkeld Road Perth PH1 3GB | Erection of a wind turbine | Application approved | |||||
Ref. No: 04/02590/FUL | Land West Of Hilton Of Duncrieve Glenfarg Perth | Erection of a wind turbine | Application approved | |||||
Ref. No 04/0004/WIND | Griffin | 68 | 124 | 156 | Operational | |||
Ref.No:03/01917/FUL | Drumderg | 16 | 108 | 32 | Operational | |||
Ref. No: 03/01729/FUL | Zwetsloot Flower Wholesaler Thorngreen Road Kinrossie Perth | Erection of a 15m high wind turbine | Application approved | |||||
Ref. No: 02/00089/MOD | Pond Cottage, Hattonburn Milnathort Kinross | Modification of existing consent to erect 10m mast for wind turbine for electricity generation at | Application approved | |||||
Ref. No: 00/00482/FUL | Langside Braco Dunblane Perthshire FK15 9LN | Alterations to house and erection of double garage and wind turbine at | Application approved | |||||
Ref. No: 99/00108/FUL | Druimantavore Steading Crieff Perthshire PH7 4JR | Erection of a Proven Wind Turbine at | Application approved |
Hydro schemes
Search the online database of hydro planning applications for hydro schemes or view applications below:
Proposal | Location | Developer | Installed capacity (MW) | Status |
---|---|---|---|---|
Ardtalnaig (opens new window) | Ardtalnaig | Achomer Energy | 1.7 | Awaiting decision |
Riemore Estate (opens new window) | Butterstone | Buckny Hydro | - | Withdrawn |
Shian Burn (opens new window) | Amulree | Garrows Farm | 0.08 | Withdrawn |
Ballbeg Farm (opens new window) | Lawers | P McDiarmid and Co | 0.1 | Approved |
Invervar (opens new window) | Glenlyon | Green Highland Renewables | - | Amended application |
Remony (opens new window) | Aberfeldy | Achard Hydro | 0.45 | Awaiting construction |
Lick (opens new window) | Foss | Frenich Hydro | 0.63 | Awaiting construction |
Allt Meurain (opens new window) | Glen Lyon | Glen Meran Farming | 0.80 | Awaiting decision |
Eas Eoghannan (opens new window) | Glen Lyon | Glen Meran Farming | 0.80 | Awaiting decision |
Allt Lairig Nan Lunn (opens new window) | Glen Lyon | Lubreoch Farming | 0.80 | Awaiting decision |
Dowally Burn (opens new window) | Dowally | Blair Castle Estate | 0.50 | Under construction |
Banvie Burn (opens new window) | Blair Atholl | Blair Castle Estate | 0.50 | Under construction |
Loch Broom (opens new window) | Ballinluig | Blair Castle Estate | 0.50 | Under construction |
Mill of Keithick (opens new window) | Coupar Angus | Keithick Farms | 0.034 | Awaiting construction |
Glenfernate (opens new window) | Enochdhu | Glenfernate Farm Partnership | 0.075 | Awaiting construction |
Fealar Lodge (opens new window) | Enochdhu | Fearlar Grazings | 0.05 | Awaiting construction |
Oakbank Mill (opens new window) | Blairgowrie | Blairgowrie & Rattray Regeneration Company | 0.05 | Awaiting construction |
Alt-Da-Ghob-Burn (opens new window) | Glenlyon | CA Ramsay Partnership | 0.60 | Approved |
Roroyere (opens new window) | Glenlyon | Green Highland Renewables | 0.75 | Approved |
West of Roromore (opens new window) | Glenlyon | Ingleby 451 Ltd | 0.95 | Approved |
Camusvrachan (opens new window) | Glenlyon | Camusvrachan Hydro | 0.75 | Approved |
Urlar (opens new window) | Aberfeldy | Urlar Estate | 0.985 | Approved |
Inverinain (opens new window) | Glenlyon | CA Ramsay Partnership | 0.85 | Approved |
Innerwick Burn (opens new window) | Glenlyon | Innerwick Hydro | 1.00 | Approved |
Kinnarird Burn (opens new window) | Pitlochry | Old Faskally Farming Company | 0.25 | Approved |
River Braan (opens new window) | Dunkeld | npower | 3.40 | - |
Innerhadden Estate (opens new window) | Kinloch Rannoch | Innerhadden Hydro Ltd | 1.40 | Approved |
Keltneyburn (opens new window) | Aberfeldy | Keltneyburn Hydro Ltd | 2.20 | Approved |
Allt A' Bhealaich (opens new window) | Aberfeldy | Bolfracks Estate | 0.85 | Approved |
Falls of Camserney (opens new window) | Camserney | Camserney Hydro Scheme Ltd | 1.20 | Operational |
Beauly to Denny transmission line
When completed, the project will replace the existing transmission line with fewer but taller pylons; this is intended to facilitate the growth of the renewable energy sector in the north and west of Scotland by making it possible to feed the power generated into the wider National Grid. After a Public inquiry the Scottish Ministers approved the application and construction is now well under-way with completion expected in 2015.