Latest updates
Main flood scheme construction
The main construction operations to form the flood defences are now progressing. A short section of steel sheet-piling has been carried out along Strowan Road. This is to provide a below ground seepage cut off behind the new flood defences. The steel sheet piles remain visible currently but will be cut down to below road level.
The next location for piling works will be south of Camp Road, and this will commence after mid-April.
Noise and vibration monitoring has been set up and will be continuously monitored during the works.
Site set up
The main site compound is situated located to the south-east of Dalginross on agricultural land (off the South Crieff Road).
There is a satellite compound situated at the Field of Refuge car park. This will remain in place for the construction period (October 2026). Balfour Beatty have recently reviewed their current requirements and have made part of the car park available for public use again temporarily. They will require to take over the full car park area again in the future as the flood scheme works near this area. We will provide notice in advance of this.
We recognise that this is a well-used parking area and apologise for any inconvenience this may cause.
Site clearance work - Tree removal works
The majority of trees that need to be removed for the works have now been cleared. We do not anticipate any further tree clearance, but in the event we find any significant root systems within the working area further tree clearance will be required.
Stockpiled materials will be removed from site once suitable vehicular access has been formed to the less accessible areas.
We recognise the impact that this tree felling can have, but unfortunately this is an unavoidable consequence of constructing the important flood defences in Comrie.
The design of the scheme has tried to minimise the number of trees being removed, and we will continue to work with the contractor to retain as many trees as is practical to do so. Some of the trees that will be removed are close to the end of their natural lifespan and so would likely have been subject to future removal.
As part of the scheme, we will replant three trees for every one tree that is felled. This will form part of the wider landscaping and re-instatement work after the defences are constructed. It will not always be possible to replant trees close to where they have been felled, due to the new flood defences, but we have identified areas within the wider Comrie area which can accommodate, and benefit, from the compensatory planting.
Road closures
The Flood Protection works will have an impact on the road network. The latest road closures (active or proposed) are shown below:
Road / Street | Details | Dates | Reason |
---|---|---|---|
Strowan Road | Full road closure between Dalginross Bridge and Glebe Road (Closure in 4 Phases to maintain residential access) | 13/02/25 - 31/07/26 | To construct main flood defences along Strowan Road |
A85 (Station Rd) | Temporary traffic lights between Comrie Holiday Park and A85 Lednock Bridge | 13/02/25 - 31/08/2026 | To operate the widened access for construction vehicles |
Path closures and diversions
The Flood Protection works will have an impact on the path network in Comrie. The affected routes are stated below and in our Core Path Diversions (PDF, 566 KB).
Path | Details | Dates |
---|---|---|
Field of Refuge/Camp Road (CMRI/14) | Closure with diversion route | January 2025 - August 2026 |
Lochay Drive (CMRI/35) | Closure with diversion route
| January 2025 - July 2026 |
Nurses Lane (CMRI/43) | Not closed but path users will be segregated from construction traffic. | January 2025 - June 2026 |
Construction photographs and drone surveys
Monthly drone surveys will be flown throughout the construction phase to record and display progress of the project. The latest surveys can be viewed below.
Project timeline
Projects of the scale and complexity of the Comrie flood protection scheme will encounter challenges that can slow down progress. The project has experienced some delays for various reasons, and we would like to thank the community for their ongoing patience.
However, the project has now reached a significant milestone with the commencement of the main construction works contract, which was awarded to Balfour Beatty in August 2024.
View the current timeline (PDF, 539 KB). This will be updated as we progress through the main construction phase.
Community liaison
The Council is continuing to liaise with residents and landowners directly affected by the flood scheme works. We will continue to meet with affected residents and discuss any questions they may have.
Balfour Beatty have appointed Ben Ferguson as their Public Liaison Officer for the project. Ben will be in touch with all residents who will have a direct interface with the project, between now and the end of the year well in advance of works taking place at or adjacent to their properties / locations.
If you have any queries about the construction of the project, you can speak to the Balfour Beatty team on site or by contacting Ben on 07732 079276 or by emailing ComrieAdmin@balfourbeatty.com .
Community drop-in sessions
The most recent community drop in session was held on Thursday 6 February 2025 at the White Church (2-7pm in the Ruchill Hall). This was well attended and enabled the community to meet representatives from the Council's project team and the Contractor, and to discuss the scheme and any queries they may have
The exhibition materials from these events are available to view on the scheme documents page.
The Council will continue to keep the community informed of progress. We will issue community newsletters regularly throughout the construction phase to keep the community updated, with the next one scheduled for June 2025. Please find a link to the most recent community newsletter below:
Current newsletter
Previous newsletters
- Comrie flood newsletter 11 - December 2024 (PDF, 652 KB)
- Comrie flood newsletter 10 - September 2024 (PDF, 278 KB)
- Comrie flood newsletter 9 - May 2023 (PDF, 435 KB)
- Comrie flood newsletter 8 - April 2022 (PDF, 292 KB)
- Comrie flood newsletter 7 - September 2021 (PDF, 387 KB)
- Comrie flood newsletter 6 - February 2020 (PDF, 267 KB)
- Comrie flood newsletter 5 - November 2019 (PDF, 715 KB)
- Comrie flood newsletter 4 - April 2019 (PDF, 308 KB)
- Comrie flood newsletter 3 - January 2019 (PDF, 523 KB)
- Comrie flood newsletter 2 - June 2018 (PDF, 310 KB)
- Comrie flood newsletter 1 (PDF, 1 MB)
Contact details
If you have any queries relating to the Comrie Flood Protection Scheme please contact Ross Fletcher, Project Manager, or Gavin Bissett, Engineer (Flooding), on 01738 476840 or at ComrieFloodScheme@pkc.gov.uk.
Correspondence can also be addressed to the Flooding Team, Environment and Infrastructure, Perth and Kinross Council, Pullar House, 35 Kinnoull Street, Perth, PH1 5GD.